Commissioner Covey’s Updates

January 13, 2023 Update from Williamson County Commissioner Covey

Great Oaks Bridge Construction

Notes:

Expected Completion—Spring 2023

This project improves the intersection of Great Oaks Dr and Brushy Creek/Hairy Man Road by improving traffic flow and raising the bridge to prevent flooding.

Please do not hesitate to contact Commissioner Valerie Covey’s office with any questions or   concerns you may have at 512-943-3370 or comm3@wilco.org

Progress this Week:

DeNucci Constructors – Removed forms from wing walls at various culvert locations.

Subcontractor Greater Austin -Poured the bridge deck on Span 1 of the Great Oaks Bridge.

Subcontractor Alpha Paving – Applied the asphalt seal coat and paved the Type B asphalt on Brushy Creek Road.

Work Scheduled:

DeNucci Constructors – Continue culvert construction along Brushy Creek Road. Continue anti-graffiti coating application to retaining walls.

Subcontractor Greater Austin – Continue Phase 3 bridge construction at bridge Bent 2.

Lane Closures:

Temporary daily lane closures are anticipated to provide a safe work zone.

The Phase 3 Brushy Creek Road truck traffic detour is in place.

General Notes:

Watch for construction equipment entering and exiting work zones, within project limits.

All work mentioned above is contingent upon weather conditions.